The goal of the Phobos version is to take care of the last important issues with Mars before we begin Jupiter. (At the time that was the plan, however there ended up being several more "last minor version before Jupiter")
[edit]
Limited spec
This page is just an overview since this version was developed before the wiki was being used for documentation.
[edit]
Key features
- Linked columns
- Synchronize forms improvement
- Form import overwrite option
- Form sorting improvement
[edit]
Timeline
- April 19, 2004 - Draft Functional Spec, introduction to developers
- April 26 - Draft Technical Spec done & Initial estimates done
- April 26 - First schedule meeting with management
- April 27 - Primary feature development begins
- May 3 - Spec & estimate updates (all day)
- May 10 - Update announcement
- May 13 - Final development day (all tasks done)
- May 14 - Dev testing, CR fixing
- May 17 - Demos to Jade (tasks), Feature testing, CR fixing
- May 18 - Demos to Jade (feature CRs), CR fixing (all A's done) , Feature freeze
- May 19 to 21 - Dev testing, CR verification, CR fixing (A, A+ only), (Tom off)
- May 24 - Stat holiday
- May 25 to 28 - Focus testing, (Tom off 25 & 26, Tai off 28)
- May 31 - Focus testing reports due, CR fixing (A, A+ only)
- June 1 - CR fixing (A, A+ only)
- June 2 to June 4 - "Every page" testing, CR verification, CR fixing (A+ only)
- June 7 - CR verification, CR fixing (A+ only), Deployment of demo to Baggett, Executive demo
- June 8 - 9 - "Just in case" days (start on next version if no more Phobos work)
- June 9 evening - Deployment to Intelisys & Agent RPM
[edit]
Codename
Continues our Solar System naming. All 3.x versions should be Mars related.